01 / The short answer
Four to twelve weeks for most business websites
A small marketing site with five to eight pages usually takes four to six weeks from kick-off to launch. A larger site with a blog, booking or a shop is closer to eight to twelve. Anything with custom logic, logins or integrations is a different conversation and is measured in months, not weeks.
Those numbers assume one thing that surprises most clients: the build itself is rarely the slow part. Waiting is.
02 / Where the time goes
A typical six-week project, week by week
- Week 1: discovery. Goals, audience, sitemap, the pages that matter and the content you already have.
- Weeks 2 to 3: design. Homepage first, then the key inner pages. One or two rounds of feedback.
- Weeks 3 to 5: build. Templates, content entry, forms, integrations, mobile layouts.
- Week 6: review and launch. Testing on real phones, speed checks, redirects from the old site, going live.
Overlap is normal. Development can start on approved pages while the rest of the design is still being reviewed.
03 / What slows it down
Content, decisions and too many reviewers
The single biggest cause of delay is content. A designer can lay out a page without final words, but you cannot launch it. If your team is writing the copy, start on day one, not after the design is approved.
The second is decisions by committee. Five people giving feedback on a homepage produces five directions and a week of meetings. Pick one person who has the final say and let them gather everyone else’s comments first.
The third is scope that grows mid-project. Adding a members area in week four is possible, but it moves the launch date. Note new ideas for phase two instead.
04 / How to stay on the short end
Four things you can do before kick-off
- Collect your logo files, brand colours and photos in one shared folder.
- List the five pages that bring in work and write those first.
- Look at three competitor sites and note what you like and dislike about each.
- Block an hour a week in your calendar for reviews, so feedback never waits.
Clients who arrive with this done routinely launch two to three weeks earlier than those who do not.
05 / A word on fast quotes
Be careful with a promise of one week
A website can be put up in a week. A website that brings in enquiries, loads fast on a phone and is easy for your team to update needs time to plan. If a quote promises a full site in days, ask what is being skipped. Usually it is the thinking.